Skip to content

Government plans to rebuild West Fraser Road

Funding is in place and plans are moving ahead to rebuild and realign West Fraser Road, replacing the road that was heavily damaged by flooding in 2018.

Once complete, the new road will provide local people with a safe, reliable and efficient roadway to get to and from their homes, schools, jobs and appointments.

In April 2018, high water levels from the spring freshet caused Narcosli Creek to erode five sections of West Fraser Road on the west side of the Fraser River, approximately 17 kilometres south of Quesnel. The damage was severe, resulting in the road being closed over a three-kilometre section.


The ministry is finalizing the detailed design for the new road, which will bypass the active slide areas along the section washed out in 2018. Work will include the construction of five kilometres of two-lane road on a new alignment, a new bridge crossing Narcosli Creek and rock stabilization work along the new route.

Upon completion of the final engineering design activities, the ministry will hold a public information session in spring 2020 to share the finalized design and project timelines. Construction is expected to begin later this year. Completion is slated for late 2022.

Since the washout, a detour route has been in place via the Garner and Webster Lake Road system. Government has invested nearly $2 million to improve the route. Local ministry staff and the maintenance contractor continue to ensure the detour remains safe and reliable for road users.

The project, which is estimated to cost up to $103.4 million, has been approved in principle for funding support through Public Safety Canada’s Disaster Financial Assistance Arrangement.

West Fraser Road provides access to the ?Esdilagh First Nation community, ranches, logging activities, farming lands and local residences.

Leave a comment

Your email address will not be published. Required fields are marked *